Maintenance Details
| Date | 30 Jun 2020 |
|---|---|
| Start Time | 07:30:01 |
| End Time | 16:30:01 |
| Nature Of Maintenance | Mechanical |
| Equipment | PUMP |
| Type of Maintenance | Scheduled Maintenance |
| Details | WATER CIRCULATION PUMP 1,2,3, it is ok. we greasing no. 2 pump. FURNACE 1 GRANULATION PUMP 1,2 greasing is done on the coupling. we change glad rope of no. 1 pump. SUBMERSIBLE PUMP 1,2, POLLUTION WATER PUMP NO 1 its monoblock hole is going big. It leakage too much water. FURNACE 2 GRANULATION PUMP 1,2, its coupling greasing is done. and we tight gland rope. POLLUTION WATER PUMP NO 1, its monoblock is leakage too much water. OFFICE SUBMERSIBLE PUMP 1, WASHING PLANT SUBMERSIBLE PUMP 1 1. check the pump condition and check discharge. 2. check coupling condition, alignment, and do greasing. 3. check pipelines and valve's condition. 4. check cooling towers nozzles condition. its nozzle condition is good. |
| Remark | |
| Furnace | Other |
| Status | Completed |