SAFAL/P/MN ORE/01.05/2021


Contract NumberSAFAL/P/MN ORE/01.05/2021
Contract Date01 Jan 2021
TypePurchase
Supplier NameDebansy Engineering Ltd
Description of Goods Manganese Ore
GradeHigh (44% - 50%)
Size10-120MM
SpecificationsMn 40% +
Quantity5000
Weight UnitMetric Tonne
DestinationSAFAL, Kanona
Rate53
CurrencyZambian Kwacha
VAT %0
Mode/Terms of Payment100% Upon delivery
Terms of DeliveryEx mine MRT inclusive
Delivery PeriodJan - Feb 2021
Dispatch ThroughBuyer Hired trucks
Lot NumberDebansy Engineering Mn Ore
Remark
Other Reference(s)
Showing 61-80 of 119 items.
#Supply DateSupplier NameItemGrade (%)Inward Quantity
6120 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)27.325
6220 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)42.145
6321 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)35.42
6422 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)26.17
6522 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)43.64
6622 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)47.075
6722 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)41.83
6823 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)26.12
6923 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)36.395
7023 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)40.925
7123 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)40.745
7223 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)39.44
7323 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)40.53
7424 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)43.365
7524 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)39.145
7624 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)40.64
7725 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)41.235
7825 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)39.365
7926 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)39.355
8026 Feb 2021Debansy Engineering LtdManganese OreHigh (44% - 50%)41.465

Total Supply: 4965.57