Maintenance Details


Date04 Jun 2020
Start Time07:30:01
End Time16:30:01
Nature Of MaintenanceMechanical
EquipmentCHIPPING YARD CRANE NO. 2
Type of MaintenanceScheduled Maintenance
DetailsCHIPPING YARD E.O.T. CRANE 2

LT.
1. checked coupling, shaft, and pedestal bearing condition it is good. Greasing is done.
2. check the gearbox oil level. It is ok no leakage.
3. check all fasteners and mounting bolts.it is ok.
4. check frame welding conditions.it is ok.
5. check end traveling gears condition. It is ok and greasing is done.

CT
1. checked coupling, shaft, and pedestal bearing condition it is good. Greasing is done.
2. check the gearbox oil level. It is ok no leakage.
3. check all fasteners and mounting bolts.it is ok.
4. check frame welding conditions.it is ok.
5. check end traveling gears condition. It is ok and greasing is done.

HT
1. checked rope drum, hook, rope condition. It is ok.greasing of rope is done.
Remark
FurnaceOther
StatusCompleted