SAFAL/P/MN ORE/07.62/2020
| Contract Number | SAFAL/P/MN ORE/07.62/2020 |
| Contract Date | 29 Jul 2020 |
| Type | Purchase |
| Supplier Name | Kampoko Resources Ltd |
| Description of Goods | Manganese Ore |
| Grade | Medium (38% - 44%) |
| Size | 10-100MM |
| Specifications | Mn- 40% Min |
| Quantity | 12000 |
| Weight Unit | Metric Tonne |
| Destination | SAFAL, Zambia plant |
| Rate | 45 |
| Currency | US Dollar |
| VAT % | 16 |
| Mode/Terms of Payment | 100% after dispatch and testing at SAFAL lab |
| Terms of Delivery | Ex Mine loaded on trucks with documents - MRT INCLUSIVE |
| Delivery Period | August- December 2020 |
| Dispatch Through | Buyer hired trucks |
| Lot Number | Kampoko Mine MG Lumpy 2 |
| Remark | Delivery from August - December 2020 |
| Other Reference(s) | |
|---|
Showing 81-81 of 81 items.
| # | Supply Date | Supplier Name | Item | Grade (%) | Inward Quantity |
| 81 | 30 Oct 2020 | Kampoko Resources Ltd | Manganese Ore | Medium (38% - 44%) | 37.175 |
Total Supply: 2471.8